A cargo ship crashed into Baltimore's Francis Scott Key Bridge early Tuesday morning, causing a near-total collapse of the span and halting vessel traffic into and out of the Port of Baltimore.
Six construction workers are believed to have fallen from the collapsing bridge into the frigid waters of the Patapsco River below. The bodies of two of the victims have been recovered so far, while four remain missing and are presumed dead, officials said.
Two construction workers were rescued and six went missing in the immediate aftermath of the collapse, officials said. The bodies of two of the victims were recovered from the water on Wednesday amid ongoing search and recovery efforts, while four remain missing and are presumed dead, officials said.
Mar 29, 2024, 11:22 PM EDT
Unified Command plans to dispatch an additional 7 cranes, 10 tugs and 8 barges
The Unified Command dispatched the Chesapeake 1000 early Friday morning and plans to dispatch an additional seven cranes, 10 tugs and nine barges over the next 120 hours.
-ABC News’ Sam Sweeney
Mar 29, 2024, 4:28 PM EDT
3 crane barges from US Navy arrive in Baltimore, 4th coming next week
Three cranes from the U.S. Navy have arrived in Baltimore to remove submerged portions of the bridge, and a fourth crane is set to arrive next week, the Navy said.
The Chesapeake has a 1,000-ton lift capacity, the Ferrell has a 200-ton lift capacity and the Oyster Bay has a 150-ton lift capacity, the Navy said.
The collapsed Francis Scott Key Bridge is shown after being struck by a cargo ship on March 26, 2024 in Edgemere, Md.
Kena Betancur/Getty Images
"Work will focus on disassembling and removing the bridge section by section. The disassembled pieces will be lifted onto barges, which will then be transported away," the Navy said in a statement. "An additional 12 crane and support vessels to include tugs, survey, dive and crew boats, are in the mobilization process and will arrive to Baltimore in the coming days."
Mar 29, 2024, 2:49 PM EDT
Freight nearly size of Eiffel Tower, shipping containers 'ripped in half as if they were papier-maché'
Maryland Gov. Wes Moore on Friday outlined several goals in the aftermath of the bridge collapse, describing the scope of the disaster as a freight nearly the size of the Eiffel Tower "with the Key Bridge resting on top of it," and shipping containers "ripped in half as if they were papier-maché."
Moore told reporters the Unified Command continues to focus on recovery efforts to help bring "closure" to victims’ families.
A search team uses a remotely operated underwater vehicle to look at the wreckage of the Francis Scott Key Bridge, which was destroyed when a cargo ship collided with it earlier this week, on March 29, 2024 in Baltimore.
Chip Somodevilla/Getty Images
He said as soon as conditions in the water are safe enough, divers will go back in the water to look for the four victims who are still missing.
Another priority is clearing the blocked channel, he said, stressing that the Port of Baltimore must reopen for the "health" of the Maryland economy and U.S. economy.
Moore also promised to rebuild the bridge, and to take care of everyone impacted by the crisis, including the families, workers, businesses and first responders.
19:29
Gov. Moore: 'We are going to rise to meet this moment'Maryland Governor Wes Moore says rebuilding the collapsed Francis Scott Key Bridge will wait for the wreckage to be cleared.
ABCNews.com
Mar 29, 2024, 2:37 PM EDT
Biden to visit Baltimore next week
President Joe Biden plans to visit Baltimore next week with Maryland Gov. Wes Moore, he told reporters on Friday.
A crane is seen near the wreckage of the Francis Scott Key Bridge on March 29, 2024 in Baltimore.
Steve Ruark/AP
The Biden administration approved $60 million in emergency relief funds for rebuilding the bridge hours after receiving the request from the state of Maryland, the White House said Thursday.
"The federal emergency funds we're releasing today will help Maryland begin urgent work, to be followed by further resources as recovery and rebuilding efforts progress," Transportation Secretary Pete Buttigieg said in a statement. "President Biden has been clear: the federal government will do everything it takes to help rebuild the bridge and get the Port of Baltimore back open."
Crushed shipping containers are seen on the bow of the Dali after it struck the Francis Scott Key Bridge, on March 29, 2024 in Baltimore.